Managing Construction Price Inflation – part 3

Below is the third and final entry in this series. For reference, Part 2 can be found here and Part 1 here.

Can I lawfully terminate a contract if inflation makes it commercially unviable?

Termination is unlikely to be an option if the supplying party has made what has become a bad bargain and the contract itself does not provide for such a remedy in the relevant circumstances.

It is also a risky strategy because if the terminating party gets it wrong and unlawfully terminates, then it runs the risk of a claim being made against it for breach of contract. The damages claimed will include the additional costs of getting the work completed by others, as well as the costs and expenses incurred as a result of wrongful termination. Any party contemplating termination of a contract should carefully consider and/or seek advice on its terms, the circumstances that give rise to termination and the consequences if that step is taken.

Depending on the precise circumstances, the following may be relevant for existing contracts:

  • Does the contract have an express force majeure clause that precisely covers the post contract event giving rise to delay(s)/price increase(s) concerned. Events known about before the contract was entered into will not count. The courts will be reluctant to come to a conclusion that force majeure applies and will consider if the event in question materially undermines the commercial objective of the contract.
  • Are sanctions against Russian companies or individuals relevant? If so, does the contract deal with illegality in the circumstances? Illegality might also be a defence to any claim for non-performance by the other party.
  • Is there an express sanctions clause that relieves the supplying party of their contractual obligations? If so, does it apply?
  • After the contract was entered into, has performance become frustrated, that is impossible or radically different to what was intended, due to unforeseen circumstances which defeat the commercial purpose of the contract? This is a high legal threshold to prove and inconvenience, hardship or financial loss will not be sufficient.
  • Does the contract provide alternative remedies for shortages/delays/ price increases, for example clauses allowing for substitutions/ variations/extensions of time and can those clauses be utilised? If so, the courts are unlikely to be sympathetic to arguments that termination was appropriate.

For contracts currently being negotiated, termination clauses can be agreed for inclusion, either for specified circumstances, which will have to be carefully drafted, or for termination at will/without cause. However, a termination at will clause is currently unusual in English construction contracts.

Will works insurance cover an increase in costs if a claim is made?

Contractors’ All Risks (CAR) policies often include so-called escalation and inflation clauses to account for increases in the value of works undertaken during a construction contract.

However, CAR policies are not all the same. That which applies to a particular contract should be carefully checked to see if such a provision is included and if so, that it adequately covers not only current inflation but higher rates of inflation during the life of the project.

If the insurance cover is not adequate for a particular loss suffered and covered by the policy, the policy may contain an “average clause” proportionately to reduce the amount paid out to match the level of the policy. This means that if the insurance cover is inadequate the policy will not meet the total amount of the claim.

Is there anything else to consider?

In the current market, there is likely to be tension between employers and their funders requiring fixed prices for budgetary and funding reasons and the supply chain’s ability to deliver at fixed prices, and to a pre-determined programme, over the life of a contract. This is particularly the case for a long programme and ones that rely on materials that are in short supply.

As with COVID-19, all parties involved in construction projects are best advised to collaborate in finding solutions. More time spent planning ahead and thinking strategically about procurement is likely to be the first step towards successful cost management.