Settling a construction dispute? “Full and final settlement” may not mean what you think
Parties settling a construction dispute usually want one thing above all – finality. But does an agreement expressed to be in “full and final settlement” prevent further claims arising from the same project?
A TCC decision of 3 November 2026, United Living (South) Ltd v Dovista UK Ltd & Ors [2026] EWHC 2676 (TCC), tells us that the answer depends on the precise wording of the settlement agreement.
BACKGROUND
The case concerned alleged defects at the Wenlock Building in north London.
Earlier proceedings brought by United Living against the project architect, Hawkins Brown Limited, and others had been settled by an agreement dated 20 March 2023. The agreement was expressed to be in “full and final settlement of the Dispute”.
United Living subsequently brought further proceedings alleging fire-safety and environmental performance defects arising from the same development and the same architect’s appointment.
The architect applied to strike out the proceedings and, alternatively, sought summary judgment on the basis that the settlement agreement of 20 March 2023 had compromised the later claims. The release provision in the settlement agreement stated:
“This Agreement is in full and final settlement of the Dispute and each Party hereby releases and forever discharges all claims, rights, demands and set-offs that it has against any other party in the Dispute (‘the Released Claims’).” (clause 5.1, quoted at paragraph 44 of the judgment)
The TCC had to decide, among other things, whether the release was confined to the claims in the earlier proceedings, or also captured the claims advanced later.
THE COURT’S DECISION
The TCC dismissed the architect’s application and held that the settlement agreement did not compromise the later claims.
It held that:
- the agreement of 20 March 2023 settled “the Dispute”, which was defined by reference to the claims in issue in the earlier proceedings;
- had the parties intended to compromise potential future claims as well as the existing proceedings, they could have used clear wording to achieve this;
- the absence of such wording indicated that a broader release was not intended; and
- the settlement was therefore limited to the claims in issue in the earlier proceedings and did not prevent the subsequent claims from being pursued.
WHAT DOES THIS MEAN FOR CONSTRUCTION PARTIES?
The TCC’s decision shows that settlement agreements require careful drafting.
Parties seeking a clean break should ensure that the release clearly identifies the claims being compromised, including whether it extends beyond the existing dispute to future or unknown claims. A court will not necessarily treat “full and final settlement” as encompassing claims beyond the defined dispute.
Conversely, a party agreeing to release claims should consider carefully whether the wording could inadvertently prevent it from pursuing other claims in the future.
The key takeaway is: do not assume that “full and final settlement” speaks for itself.
Clear drafting before settlement can be crucial to avoiding further disputes over what has, and has not, been settled.
If you have any concerns about what a settlement agreement may, or may not, cover, Wedlake Bell’s Construction team would be happy to advise.
This article is for general information purposes only and does not constitute legal advice or a comprehensive statement of the law. Specific legal advice should always be sought in relation to individual circumstances.